  • Owen-Ames-Kimball Co.

School's Out for Summer

After months of waiting, the 18'x33' scoreboard has been installed for optimal field viewing. This specialty scoreboard will have customized sizing to ensure that words, numbers, and visual displays can be seen throughout the stadium. The speaker that will accompany the large screen sits at an astounding 8'x6'.




Starting on June 6, 2021 crews will beginning the demolition phase in preparation of the new and improved Mondo Track surfacing.


The new field events location. This will also soon include the new Mondo Track surfacing.


And in the final stages of completion, the front entrance and tickets booths are having some fresh paint added.



There will additions to the home side press box including an elevator lift. Both sides of the current building will be extended by 10 x12 feet.



With The view from the concession and lounge area over looking the football field and views of the scoreboard. The projects tentative completion date is set for December 2021.

15 views0 comments